How Long Does a Fire Performance Solution Take? 7 Stages

Last Updated: November 14, 2026

Quick Summary

A fire performance solution typically takes roughly two to four weeks for a simple project, four to eight weeks for a moderate one, and eight to sixteen weeks or more for a complex building. The total splits into two stages: briefing and scoping, then analysis, modelling and draft reporting, with certifier review and revisions running on a separate clock.

  • The brief and scope stage can take one to two weeks when the design team supplies complete information.
  • The single biggest variable is how quickly complete information and decisions arrive from the design team and certifier.
  • Allow one to three weeks for a referral agency response, and longer if further information is requested.
  • One to two revision rounds is common, each adding one to three weeks depending on response times.
  • Engage the fire engineer at concept stage, not at construction documentation, to avoid redesign.
How long will your fire performance solution take?Send FyreWise your plans for a scope and timing estimate on your project.

Send Your Plans

Table of Contents

The Fire Performance Solution Timeline: A Stage-by-Stage Breakdown

A fire performance solution is an alternative compliance pathway under the National Construction Code that uses engineering analysis to prove a building meets its fire safety goals, rather than following Deemed-to-Satisfy provisions to the letter. A common question is how long a fire performance solution takes, and the honest answer is that no single figure fits every project. The work usually breaks into two stages, and each one has its own clock. Below, we walk through both stages, then show how complexity and certifier involvement stretch or shrink the total.

Architect and engineer reviewing a fire performance solution plan on a timber table in a bright design studio.
Architect and engineer reviewing a fire performance solution plan on a timber table in a bright design studio.

Stage 1: Briefing, Scoping and Information Gathering

The fire engineering design brief is where the clock starts. This stage defines the design objectives, the performance requirements in play, and the scope of work. It gathers drawings, building classification details, and any proposed design deviations. A brief and scope stage can take one to two weeks when the design team supplies complete information. Stakeholder consultation with the building certifier often begins here, and early pre-consultation is one of the best ways to avoid rework later.

Stage 2: Analysis, Modelling and Draft Reporting

Next comes the engineering analysis: fire modelling, risk assessment, egress checks, and verification against the relevant assessment method. The fire engineer then drafts the Fire Engineering Report, documenting the alternative solution and the fire safety measures it relies on. This stage varies most. A single, well-defined issue can move quickly, while a complex building with many design deviations takes longer. Expect technical review and revision rounds before the report is ready for the certifier.

How Long Each Project Complexity Takes

The duration of a fire performance solution depends largely on project complexity. A simple project with one defined issue and complete documentation can move quickly. Moderate projects add more stakeholders, more performance requirements, and more modelling. Complex projects, such as mixed-use buildings with atria or unusual egress paths, add consultation and review cycles on top. The table below summarises what drives each tier and gives indicative ranges for the whole engagement.

Project ComplexityTypical DriversIndicative End-to-End DurationWhat Speeds It Up
SimpleOne defined issue, complete drawings, single certifierRoughly two to four weeksFull information upfront, early certifier chat
ModerateSeveral deviations, multiple stakeholders, some modellingRoughly four to eight weeksPre-consultation, single point of contact, staged reporting
ComplexAtrium, unusual egress, heavy modelling, referral agenciesRoughly eight to sixteen weeks or moreEarly engagement, staged reporting, agreed decision-maker

The single biggest variable is often how quickly complete information and decisions arrive from the design team and certifier.

Time Required From Each Participant

Breaking the total into who does what makes the schedule easier to plan and to hold people to.

  • Design team (architect, services engineers): response time is the main lever. Supplying complete drawings, classification details and every proposed deviation at the start can save a full revision cycle; drip-feeding information is the most common cause of slippage.

How Long Approval and Revisions Take After the Report

Report preparation and approval are often conflated, but they run on separate clocks. Once the draft Fire Engineering Report is submitted, the certifier reviews it, may refer it to a referral agency, and can request revisions. That review and revision period sits outside the drafting time and is where many timelines quietly stretch. Certifiers can accept reports faster when every non-compliance has already been identified and addressed in the solution itself.

A Project-Planning Checklist

Use this as a simple schedule check before commissioning work:

  • Confirm the building classification and every proposed design deviation in writing.
  • Assemble complete architectural and services drawings before the brief is drafted.
  • Pre-consult the certifier on the proposed performance pathway.
  • Nominate one decision-maker for stakeholder consultation.
  • Agree a staged reporting approach for complex projects so early issues are resolved before the full report is finalised.
  • Diarise certifier review and referral time separately from engineering time.

Watch out: commissioning the fire performance solution after the design is locked almost always forces redesign when a deviation surfaces, adding weeks rather than days to the total.

The Fire Engineering Design Brief: Where the Clock Starts

A Fire Engineering Brief is the scoping document that sets out the design objectives, the performance requirements, and the methods the engineer will use. It is not the same as the report. The brief frames the problem; the report answers it. Getting the brief right upfront is the single biggest lever on total time, because every later stage inherits its scope. If you are unsure how the two documents differ, you can compare the fire engineering report and brief before commissioning any work.

The Fire Performance Solution Approval Process: After the Report

Once the Fire Engineering Report is drafted, the approval process begins, and it is a distinct phase with its own duration. The building certifier reviews the report against the performance requirements and the evidence the engineer has provided, may refer it to a referral agency such as Fire and Rescue NSW, and can request revisions before issuing approval. This review and revision period sits outside the drafting time, and it is where many timelines quietly stretch.

The phase usually runs in four steps:

  1. Submission and completeness check. The certifier confirms the report addresses every non-compliance and that supporting drawings and calculations are current. Incomplete submissions are returned, which restarts the clock.
  2. Technical review. The certifier assesses whether the performance solution satisfies the relevant performance requirements and whether the fire safety measures relied on are adequately documented.
  3. Referral, where required. For certain building types the certifier must refer the report to a referral agency. Allow one to three weeks for a response, and longer if further information is requested.
  4. Revision and approval. The engineer addresses comments and resubmits. One to two rounds is common, each adding one to three weeks depending on response times.

Certifiers accept reports faster when every non-compliance has already been identified and addressed in the solution itself. Our team sometimes liaises directly with the architect, builder, and certifier so each issue is resolved in the solution rather than through repeated resubmission. If you want the full walkthrough, see how to get a fire engineering report approved.

Watch out: submitting a report before the design is frozen invites a revision request that can add a full review cycle to the approval phase.

What Causes Delays and How to Reduce Them

Delays rarely come from the engineering. They come from missing information, late design changes, and consultation that starts too late. A common mistake is commissioning the fire performance solution after the design is locked, which forces redesign when a deviation surfaces. The fix is simple:

  • Engage the fire engineer at concept stage, not at construction documentation
  • Supply complete drawings and classification details upfront
  • Pre-consult the certifier before the report is finalised
  • Nominate one decision-maker for stakeholder consultation
  • Flag every design deviation early, not during review

Watch out: incomplete drawings sent to the engineer at the start almost always return as a revision request, adding a full cycle to the timeline.

Fire Performance Solution Examples: How Duration Shifts by Project Type

Different project types shift the fire performance solution timeline in predictable ways. A residential project with a single boundary setback issue can often be scoped and reported in a matter of days once information is complete. A commercial fit-out with several deviations takes longer because more performance requirements apply. A complex mixed-use development with an atrium or alternative egress strategy adds modelling and consultation, so the report becomes a multi-week exercise. The pattern holds: the more design deviations and the more stakeholders, the longer each stage runs. For the headline timeframes, our team has set out typical performance solution timeframes in more detail.

Send Your Plans to FyreWise for a Scope and Timing Estimate

The fastest way to get a real answer on timing is to send us your plans. FyreWise delivers performance solutions at competitive prices with fast turnaround. Our chartered and RPEQ accredited engineers work with you to find the most cost-effective, practical, and workable solution, and our reports are quickly accepted by certifiers. We identify all non-compliances at the start of the project and can liaise with the architect, builder, and certifier to address every issue. Before you commit, a short phone call can show how knowledgeable a provider is, so call and ask how we would handle your fire safety issue. You can also review fee ranges and what drives pricing or explore our fire engineering services before requesting a quote.


Timelines slip when information is incomplete or the engineer is engaged too late. FyreWise scopes every issue at the start, works with your design team and certifier, and turns around well-defined solutions in two to three days. Our chartered and RPEQ accredited engineers deliver tailored, performance-based designs with full NCC compliance from concept to occupancy. Get started with FyreWise and get a clear scope and timing estimate on your next project.

Frequently Asked Questions

How long does approval of a fire performance solution take?

Approval timing sits outside the fire engineer’s control. Once the Fire Engineering Report is lodged, the certifier and any referral agencies review it, and that review period is typically the longest single wait in the process. A well-prepared report with all non-compliances identified upfront reduces the chance of a revision cycle, which is where most extra weeks are lost. Ask your engineer whether they pre-consult the certifier during the brief stage, because that conversation often shortens the formal review later.

What information does a fire engineer need to start a fire performance solution?

A brief, clear description of the issue is often enough to begin. At FyreWise, we find clients sometimes cannot explain the problem in technical terms, and they do not need to. Send the architectural drawings, the building classification, the proposed design deviation and any correspondence from the certifier. From that, the engineer can identify what is needed to achieve compliance before producing a report. Complete information provided upfront is the single biggest factor in a fast turnaround.

Can a fire performance solution be completed while building design is still underway?

Yes, and it is usually the better approach. Engaging a fire engineer during concept design lets the fire performance solution timeline run alongside architectural work rather than after it. The Fire Engineering Brief can be developed and the certifier pre-consulted while drawings are still being finalised. Waiting until construction documentation is complete can lead to late-stage redesign, because a performance solution that fails at that point may force changes across multiple disciplines.

When should I engage a fire engineer for a performance solution?

As early as the design deviation becomes apparent. If your building work steps outside the Deemed-to-Satisfy provisions, whether that is an atrium, a boundary setback or an unusual egress layout, the fire engineer should be at the table before the design is locked in. Early involvement lets the engineer shape the design around what can be proven, rather than proving a design that is already fixed. It also gives the certifier time to review the Fire Engineering Brief before the full report is written.