What fire safety information should developers provide consultants?

Last Updated: November 24, 2026

Quick Summary

Developers should provide the site plan, architectural drawings, project brief, building classification and use details, existing-site and neighbouring-property information, and any design constraints. The quality of the fire safety information you hand over decides how fast, and how cheaply, your approval moves.

  • Send one clearly dated drawing set, not three overlapping revisions.
  • At feasibility, state what you want to build and what you cannot change.
  • A brief omitting the building’s intended use often forces a redesign at your cost.
  • At construction, as-built drawings and inspection records confirm the building matches the design.
  • Send the brief first, even if it is one page, and let the drawings follow.
Is your fire safety information pack complete?FyreWise reviews your drawings, brief and site details and advises what is needed for compliance.

Send Your Project Info

Table of Contents

What fire safety information should developers provide consultants?

Developers should provide their consultant with the site plan, architectural drawings, project brief, building classification and use details, existing-site and neighbouring-property information, and any constraints that affect the design. The quality of the fire safety information you hand over decides how fast, and how cheaply, your approval moves.

Get it right early and the brief writes itself. Get it wrong and you pay for redesign later.

A 2024 exploratory study led by L. Cleef, published via ScienceDirect’s fire-risk assessment tool review, identified 26 fire-risk assessment tools for the built environment. Only a limited number could deliver even a partial fire-risk analysis of a building. The lesson for developers is blunt: no tool replaces a clear, complete information pack.

Below, we break down exactly what to supply, by stage.

Why the fire engineering consultant brief decides your approval path

The fire engineering consultant brief is the document that sets out what your project needs, what constraints apply, and what the consultant must prove to the certifier. It decides your approval path because it frames every later decision.

A brief that names the building classification, the intended use and the performance requirements gives the consultant room to solve problems. A vague brief forces assumptions.

If you want to see how the brief differs from the final report before you prepare either, read our comparison of a fire engineering report vs fire engineering brief. It explains which project stage each document supports.

Watch out: a brief that omits the building’s intended use often forces a redesign once the certifier asks questions. That redesign lands on your budget, not the consultant’s.

Building plans for fire safety assessment: drawings and documents to supply

For a fire safety assessment, supply a current architectural drawing set, a site plan, a floor plan for each level, elevations and sections, and a schedule of fire safety measures. These are the building plans a consultant needs to assess means of escape, fire compartmentation and fire resistance.

Architect and fire engineer reviewing building plans for fire safety information during a site assessment.
Architect and fire engineer reviewing building plans for fire safety information during a site assessment.

What most guides miss is how much the drawing set carries. It shows exit widths, travel distances, fire-rated walls and the location of fire detection and fire suppression equipment. Without it, the consultant cannot test the design against the National Construction Code.

Our advice: send the drawings that coordinate fire engineering with the architectural design from concept stage, not after the drawings are locked. Our guide on coordinating fire engineering with architectural design explains why early involvement saves money.

Drawing versions, file formats and information management

Send one clearly dated drawing set, not three overlapping revisions.

  • Name files by discipline, level and revision
  • Send PDFs for review and native files where the consultant needs to measure
  • Keep a single register of issued documents
  • Flag superseded drawings so nobody works from them

A common mistake is emailing a revised plan without noting what changed. The consultant then reviews the wrong set, and the report comes back late.

Existing-site and neighbouring-property information

Existing-site and neighbouring-property information tells the consultant what already stands around your development. Supply a site survey, boundary setbacks, the use and height of adjoining buildings, and any shared walls.

This matters for fire compartmentation and for how fire might spread between buildings. It also shapes exit lighting and emergency lighting design where escape routes run close to boundaries.

Fire engineer report requirements: what the brief must make possible

A fire engineer report must be able to show the certifier how the design meets the National Construction Code, whether through Deemed-to-Satisfy provisions or a performance solution.

That means the brief should state:

  • Building classification and building use
  • Occupancy numbers and how they were calculated
  • The fire safety strategy, including means of escape and fire safety measures
  • Which parts of the design are performance-based
  • Any constraints the consultant cannot change

At FyreWise, we ensure all non-compliances are identified at the start of the project. We sometimes liaise with the architect, builder and certifier to address every issue in our solutions.

For detail on what a report covers and what drives its cost, see our guide to fire safety engineering reports, costs and design briefs.

Inputs by project stage: design, planning and construction

The information you supply should shift as the project moves.

Here is how the inputs map to each stage, including the stages most guides skip.

StageWhat to supplyWhy it matters
FeasibilitySite address and title, site plan, proposed use and occupancy, gross floor area and rise in storeys, known site constraints, target programmeLets the consultant flag early whether the brief is achievable under the National Construction Code before you commit to a design
Concept designConcept architectural drawings, building classification and use, project brief, budget and programme constraints, decision-makers and approval contactsShapes the fire safety strategy while changes are still cheap
PlanningFire safety strategy, performance solution detail, fire safety schedule, certifier questions or conditions already raisedSupports the approval process and prevents the certifier returning the application
Detailed designCoordinated architectural, structural and services drawings, revised fire safety schedule, essential fire safety measures, any amended performance solutionConfirms the design still matches the strategy once other disciplines have changed it
ConstructionAs-built drawings, inspection records, revised essential fire safety measures, any site-specific variationsEnables handover and the fire safety certificate without a late redesign
HandoverFinal fire safety schedule, annual fire safety statement requirements, operation and maintenance informationSets up the building owner for ongoing compliance

At feasibility, the most useful thing you can send is not a drawing set but a clear statement of what you want to build and what you cannot change.

At concept design, the consultant needs the project brief, the building classification and the intended use together.

At planning, the fire safety strategy and any performance solution detail should be in the consultant’s hands before the certifier sees them.

At detailed design, the risk is coordination. Other disciplines change the drawings, and the fire strategy quietly drifts out of step.

At construction, as-built drawings and inspection records are the inputs that let the consultant confirm the building matches the design.

Watch out: sending detailed design drawings without the concept-stage brief forces the consultant to reverse-engineer your intent, and the report comes back late and qualified.

If you want a step-by-step process for preparing the report at the right stage, our guide on the 5 steps to prepare a fire engineering report walks through it from brief to submission under the NCC.

Your fire safety consultant project checklist

Use this checklist before you send anything to a consultant.

Project brief and constraints

  • Project description and intended building use, the consultant cannot classify the building without it
  • Building classification under the NCC, sets the Deemed-to-Satisfy baseline
  • Budget and programme constraints the consultant must respect, shapes which performance solutions are realistic
  • Decision-makers and approval contacts, tells the consultant who can approve design changes
  • Known constraints the consultant cannot change, boundaries, easements, heritage controls, existing services

Drawings and site information

  • Current architectural drawing set, dated and versioned, the basis for means of escape and fire compartmentation review
  • Site plan with boundaries and setbacks, shows how fire might spread to and from neighbouring property
  • Floor plans, elevations and sections, needed to test travel distances and fire resistance
  • Existing-site survey and neighbouring-property details, adjoining uses, heights and shared walls
  • Access constraints for fire brigade vehicles, turning circles, grades and hardstand

Compliance documents

  • Fire safety schedule and essential fire safety measures, the measures the building must maintain
  • Any existing fire safety certificate or annual fire safety statement, shows the compliance history
  • Prior reports or fire safety audit findings, prevents the consultant repeating work
  • Certifier questions or conditions already raised, the consultant can answer them directly

File management

  • One document register, a single source of truth for what has been issued
  • PDFs for review, native files where the consultant needs to measure
  • Clear note of what changed since the last issue, revision histories prevent rework
  • Superseded drawings flagged so nobody works from them

Send the brief first, even if it is one page, and let the drawings follow.

Watch out: emailing a revised plan without noting what changed can cause a report to review the wrong set.

If you want to see how the brief differs from the final report before you prepare either, read our comparison of a fire engineering report vs fire engineering brief. It explains which project stage each document supports.

Send your project information to FyreWise for review

The fastest way to test whether your information pack is complete is to send it to a fire engineer and ask. Our team offers performance solutions with fast turnaround. For current prices, visit the FyreWise pricing page or request a quote.

A brief, concise description from you is often enough for us to identify the issue. We can advise what is needed to achieve compliance before producing a report. Our solutions are generally very bespoke, and we work with you to find the most cost-effective, practical and workable option.

Not sure what to send? A phone call shows how knowledgeable a provider is before you buy. Ask us how we would handle your fire safety issues, and we will tell you plainly.


The real risk on your project is not a difficult design. It is a thin information pack that forces redesign at the worst moment. FyreWise is led by Chartered and RPEQ accredited fire engineers, with deep expertise in Building Code of Australia compliance and comprehensive support from concept design to final occupancy. You can get in touch with our team to begin.

Frequently Asked Questions

What fire safety information does a consultant need from a developer?

At minimum: the project brief and constraints, a full architectural drawing set with site plan, the proposed building classification and use, existing-site and neighbouring-property details, and any prior reports or correspondence with the certifier. Fire safety information about intended occupancy matters as much as the drawings, because it drives egress, detection and suppression decisions. Send everything at once rather than in dribs and drabs, and note which drawing revision is current.

When should a developer engage a fire safety consultant?

Before the design is locked in. Engaging a consultant at concept stage lets them flag performance solutions, fire compartmentation and means-of-escape issues while changes are still cheap. Waiting until documentation or construction means redesign, approval delays and budget overruns. At FyreWise we identify all non-compliances at the start of the project so the certifier is not discovering them later, and we can advise what is needed to achieve compliance before a report is produced.

What building details affect a fire engineering assessment?

Building classification and use, rise in storeys, floor areas and fire compartmentation, fire resistance levels, travel distances and exits, and whether the design relies on a performance solution rather than Deemed-to-Satisfy provisions. Atriums, mixed-use occupancy and unusual layouts need more detail up front. The quality of the information you supply still carries the assessment.

How should developers manage design changes during a fire engineering assessment?

Tell the consultant immediately and resend the affected drawings with a new revision number and date. Keep one register of changes so the fire safety strategy and fire engineer report always match the current design. Unmanaged changes are the usual cause of a report being rejected by the certifier or stamped not for construction. A brief, concise description of what changed is often enough for the consultant to identify the impact and advise on compliance before reissuing.